Item Coversheet

Agenda Item Summary



Ordinance # / Resolution #: SD-2023-0161 Edgewater Phase 11
Contact Person / Sponsor: A. Davis
Department: Planning
Date Requested to be on Agenda: 11/21/2023

Issue for Consideration:
N/A

Points to Consider:
  • Per Planning Commission’s Conditional Approval all outstanding comments were to be resolved prior to August 19th, 2023 (60 days from the PC meeting date);
  • Revised Preliminary Plat was submitted on October 2nd for staff review;
  • There are still outstanding TRC comments from Planning and Fire,
  • Planning staff has not been provided with any form of approval from Lancaster County Water and Sewer for this phase.
  • The only significant change to the design of the plat since the last review is the removal of a road segment connecting Street B to Street C.
  • TRC comments were distributed to the applicant on October 30th, 2023. Staff has received no revised plan or response to comments at this time (November 14, 2023).


Recommendation:

Staff recommends denial of this Major Preliminary Subdivision Plat request pursuant to the following findings of fact:

 

1. At the June 20th, 2023 Planning Commission meeting Planning Staff recommended Conditional Approval;

2. The condition of approval imposed was the Resolution of outstanding TRC Preliminary Plat comments within 60 days of the June 20th meeting (Planning, Fire, and LCWSD);

3. At time of publishing of this report (November 14, 2023) there are remaining outstanding comments from Planning, Fire, and LCWSD.

 

ATTACHMENTS:
DescriptionUpload DateType
Staff Report11/14/2023Planning Staff Report
Application10/30/2023Exhibit
Location Map10/30/2023Exhibit
Revised Preliminary Plat 10/2/202311/1/2023Exhibit
TRC Review Comments 10/30/202310/30/2023Exhibit