Ordinance # / Resolution #: SD-2023-0161 Edgewater Phase 11
Contact Person / Sponsor: A. Davis
Department: Planning
Date Requested to be on Agenda: 1/16/2024
Issue for Consideration:
N/A
Points to Consider:
- Per Planning Commission’s Conditional Approval all outstanding comments were to be resolved prior to August 19th, 2023 (60 days from the PC meeting date);
- Revised Preliminary Plat was submitted on November 19, 2023 for staff review;
- There are still outstanding TRC comments ,
- Planning staff has not been provided with any form of approval from Lancaster County Water and Sewer for this phase.
- TRC comments were distributed to the applicant on November 19th, 2023. Staff has received no revised plan or response to comments at this time (January 3, 2024).
Recommendation:
Staff recommends denial of this Major Preliminary Subdivision Plat request pursuant to the following findings of fact:
1. At the June 20th, 2023 Planning Commission meeting Planning Staff recommended Conditional Approval;
2. The condition of approval imposed was the Resolution of outstanding TRC Preliminary Plat comments within 60 days of the June 20th meeting (Planning, Fire, and LCWSD);
3. At time of publishing of this report (November 14, 2023) there are remaining outstanding comments from Planning, Fire, and LCWSD.